Pre-Task Plan: Excavating into the Side of a Hill

Date: [DATE] Work Area: [WORK AREA] Task Supervisor: [SUPERVISOR NAME]

1. Task Description

Excavating into the side of a hill to create a stable slope for construction purposes. This involves removing soil and rock while ensuring the stability of the excavation site.

2. Task Duration

Estimated Start: [START TIME] Estimated Completion: [END TIME]

3. Personnel Involved

  • Excavator Operator
  • Spotter
  • Safety Officer

4. Task-Specific Hazards and Controls

HazardRiskControl Measures
Machine instability on slopeTip/roll overEnsure machine is level, avoid swinging to downhill side, create embankment if necessary [1]
Undercutting or digging beneath overhangsLandslide or falling debrisDo not undercut or dig beneath overhangs [2]
Contact with underground utilitiesDamage to utilities, potential hazardsConfirm location of utilities before digging [1]

5. Required PPE for Today's Task

  • Hard hat
  • High-visibility vest
  • Steel-toed boots
  • Safety goggles

6. Tools and Equipment Needed

  • Excavator
  • Shovels
  • Soil compactor

7. Pre-Start Checklist

Area Preparation

  • Confirm utility locations and mark them [1]
  • Clear area of loose debris and materials
  • Ensure spoil piles are at least 1 meter from the edge of the excavation [3]

Equipment Checks

  • Inspect excavator for mechanical issues
  • Ensure all safety guards are in place
  • Check communication devices

Communication

  • Establish hand signals with spotter
  • Ensure all team members have radios

8. Task Steps Overview

  1. Conduct site inspection and mark utilities.
  2. Set up equipment and ensure stability on the slope.
  3. Begin excavation, maintaining a safe distance from marked utilities.
  4. Monitor slope stability and adjust as necessary.
  5. Safely dispose of excavated materials.

9. Emergency Response for This Task

  • Machine instability → Evacuate area and stabilize machine
  • Utility strike → Stop work immediately and notify utility company

10. Task-Specific Precautions

  • Maintain a safe distance from the edge of the excavation.
  • Use a spotter to guide machine movements.
  • Regularly inspect the slope for signs of instability.

Pre-Task Briefing Confirmation

All workers understand the task, associated hazards, and required controls.

Team Lead Initials: [___] Date: [DATE] Time: [TIME]

Safety powered by SALUS


Important Safety Note:

Always verify safety information with your organization's specific guidelines and local regulations.

References

Page links are approximate
[1]↑

Kobelco SK200-10, SK210LC-10 Operation Manual

Open Document

Page 53

[2]↑

Kobelco SK200-10, SK210LC-10 Operation Manual

Open Document

Page 54

[3]↑

Occupational Health and Safety Code

Open Document

Page 233

  • Terms of Service
  • Privacy Policy
  • Safety powered by SALUS