Pre-Task Plan: Excavating into the Side of a Hill
Date: [DATE] Work Area: [WORK AREA] Task Supervisor: [SUPERVISOR NAME]
1. Task Description
Excavating into the side of a hill to create a stable slope for construction purposes. This involves removing soil and rock while ensuring the stability of the excavation site.
2. Task Duration
Estimated Start: [START TIME] Estimated Completion: [END TIME]
3. Personnel Involved
- Excavator Operator
- Spotter
- Safety Officer
4. Task-Specific Hazards and Controls
Hazard | Risk | Control Measures |
---|---|---|
Machine instability on slope | Tip/roll over | Ensure machine is level, avoid swinging to downhill side, create embankment if necessary [1] |
Undercutting or digging beneath overhangs | Landslide or falling debris | Do not undercut or dig beneath overhangs [2] |
Contact with underground utilities | Damage to utilities, potential hazards | Confirm location of utilities before digging [1] |
5. Required PPE for Today's Task
- Hard hat
- High-visibility vest
- Steel-toed boots
- Safety goggles
6. Tools and Equipment Needed
- Excavator
- Shovels
- Soil compactor
7. Pre-Start Checklist
Area Preparation
- Confirm utility locations and mark them [1]
- Clear area of loose debris and materials
- Ensure spoil piles are at least 1 meter from the edge of the excavation [3]
Equipment Checks
- Inspect excavator for mechanical issues
- Ensure all safety guards are in place
- Check communication devices
Communication
- Establish hand signals with spotter
- Ensure all team members have radios
8. Task Steps Overview
- Conduct site inspection and mark utilities.
- Set up equipment and ensure stability on the slope.
- Begin excavation, maintaining a safe distance from marked utilities.
- Monitor slope stability and adjust as necessary.
- Safely dispose of excavated materials.
9. Emergency Response for This Task
- Machine instability → Evacuate area and stabilize machine
- Utility strike → Stop work immediately and notify utility company
10. Task-Specific Precautions
- Maintain a safe distance from the edge of the excavation.
- Use a spotter to guide machine movements.
- Regularly inspect the slope for signs of instability.
Pre-Task Briefing Confirmation
All workers understand the task, associated hazards, and required controls.
Team Lead Initials: [___] Date: [DATE] Time: [TIME]