Pre-Task Plan: Ceiling Grid Installation
Date: [DATE] Work Area: [WORK AREA] Task Supervisor: [SUPERVISOR NAME]
1. Task Description
Installation of ceiling grid components according to project specifications.
2. Task Duration
Estimated Start: [START TIME] Estimated Completion: [END TIME]
3. Personnel Involved
- Installers
- Supervisor
- Spotter
4. Task-Specific Hazards and Controls
Hazard | Risk | Control Measures |
---|---|---|
Working at Heights | Falls resulting in serious injury or death | Use appropriate fall protection equipment, including personal fall arrest systems. Ensure proper anchorage points are used [1]. Inspect fall protection equipment before use. |
Falling Objects | Injury to workers below | Implement overhead safeguards to protect workers from falling objects [2]. Use wire mesh or equivalent material on scaffolds to prevent objects from falling [3]. Establish a controlled access zone below the work area. |
Unstable Scaffold | Scaffold collapse leading to falls | Ensure scaffold is erected by a competent person and inspected before use. Use guardrail systems with minimum 200-pound toprail capacity [4]. Ensure proper bracing and ties are in place 14, 18. |
Electrical Hazards | Electrocution or burns | Identify and avoid all electrical sources. Use non-conductive ladders. |
Sharp Edges of Grid | Cuts and lacerations | Wear appropriate gloves. Use caution when handling grid components. |
5. Required PPE for Today's Task
6. Tools and Equipment Needed
- Measuring tape
- Laser level
- Drill
- Screw gun
- Utility knife
- Scaffolding or ladders
7. Pre-Start Checklist
Area Preparation
- Clear the work area of obstructions.
- Ensure adequate lighting is available [6].
- Barricade the area below to prevent unauthorized access [3].
Equipment Checks
- Inspect all tools and equipment for defects.
- Verify that scaffolding is stable and properly erected.
- Check fall protection equipment for wear and tear.
Communication
- Review task-specific hazards and controls with all workers.
- Establish clear communication signals between workers.
8. Task Steps Overview
- Measure and mark the ceiling for grid layout.
- Install perimeter wall angles.
- Suspend main tees from the ceiling.
- Install cross tees to complete the grid.
- Inspect the grid for proper alignment and stability.
9. Emergency Response for This Task
- Fall from height → Activate emergency response system, provide first aid, and investigate the incident.
- Electrical shock → Shut off power, provide first aid, and seek medical attention.
10. Task-Specific Precautions
- Never work directly below another worker.
- Use tag lines when hoisting materials.
- Keep the work area clean and free of debris [6].
Pre-Task Briefing Confirmation
All workers understand the task, associated hazards, and required controls.
Team Lead Initials: [___] Date: [DATE] Time: [TIME]
Safety powered by SALUS
Important Safety Note:
Always verify safety information with your organization's specific guidelines and local regulations.
References
Page links are approximate[4]↑
Rules for the Administration of the Oregon Safe Employment Act (Construction, Division 3, OSHA Oregon)
Open DocumentPage 535